It is based on section 4(1)(s) of the Standards Act No. 2 of 2009. Verification is carried out by TBS-approved service providers through physical inspection, laboratory testing, document review and, where needed, factory audits. TBS publishes the list of regulated HS codes (the current list is dated 29 March 2025), a PVoC guideline, a list of exempted categories and criteria, and a penalty schedule for uninspected goods; check whether each item in your line is on the regulated list or exempt. For a production line, the practical step is to sequence the PVoC inspection with the factory acceptance test in China, so that one inspection window covers both and the CoC is in hand before sailing. PVoC is separate from duties: capital goods generally pay 0% under the EAC Common External Tariff, and VAT at 18% may be deferred for qualifying capital goods.

Regulations change. Confirm the current requirement with the authority named in each section before you commit money.

What PVoC is

PVoC is a conformity check done in the exporting country, before shipment. Its purpose is to stop goods that do not meet Tanzanian standards from arriving, protecting consumers' health and safety, preventing unfair competition from substandard imports and avoiding the cost of destroying or re-exporting goods at the port. TBS publishes the procedure, the regulated product list and the partner service providers on its website.

Authority: Tanzania Bureau of Standards (TBS), under the Standards Act No. 2 of 2009.

Does your machinery fall under PVoC?

PVoC applies to the goods whose HS codes are on TBS's regulated list. Many consumer goods, building materials, electrical products, food and chemicals are regulated; whether a given machine, spare part or component is covered depends on its code. For a production line:

  1. Classify each item to its HS code with your supplier and clearing agent.
  2. Check each code against TBS's current list of regulated HS codes.
  3. Check the exemptions: TBS publishes exempted categories and criteria, which may cover some capital goods or project imports under conditions.
  4. Ask TBS or an approved service provider if you are unsure, before shipping.

Spare parts, electrical cables, panels and consumables shipped with a line may be regulated even when the main machine is not.

The steps for a regulated shipment

StepWhat happens
RequestThe exporter or importer applies to a TBS-approved PVoC service provider for the exporting country
DocumentsPro-forma invoice, packing list, product descriptions, test reports and certificates where available
InspectionPhysical inspection of the goods before shipment; laboratory testing where needed
Factory auditWhere needed, to confirm production and quality control
CoC issuedIf the goods conform, a Certificate of Conformity is issued
ShipmentGoods ship with the CoC and other clearance documents
ClearanceThe CoC is presented at clearance in Tanzania

Authority: TBS, through its approved PVoC service providers.

Plan PVoC with the factory acceptance test

For a production line, the factory acceptance test (FAT) in China is when the line is assembled and run before packing. Arranging the PVoC inspection in the same window lets the inspector see the equipment complete, check documents and labels, and take any samples, without a second trip or a delay at the port. Agree in the contract that the supplier will support the PVoC inspection, provide the documents and test reports needed, and not ship until the CoC is issued.

What happens without a CoC

According to TBS, regulated goods arriving at Tanzanian ports without a CoC will be rejected or fined. TBS also runs destination inspection for certain goods and publishes a penalty schedule for uninspected goods regulated under PVoC. The cost is not only the penalty: storage, demurrage, testing and delays to installation can cost more. Treat the CoC as part of the shipping documents, like the bill of lading.

Duties and VAT: separate from PVoC

PVoC is about standards; duties and taxes are handled by the Tanzania Revenue Authority. Under the EAC Common External Tariff, capital goods generally pay 0% duty, intermediate goods 10% and consumer goods 25%, depending on the exact tariff code. VAT on imports is 18%. Tanzania allows VAT deferment on qualifying capital goods, and the Finance Act, 2026 retained the deferment; check the current conditions and your eligibility with TRA before ordering. Our guide to importing a production line into Tanzania covers the full route.

Authority: Tanzania Revenue Authority (TRA).

Used equipment

TBS has separate PVoC rules for used motor vehicles, and used goods in general may face extra scrutiny or restrictions. If any part of your line is second-hand, check with TBS before buying it.

Documents to prepare

  • Pro-forma and commercial invoices with clear descriptions and HS codes for each item.
  • Packing list matching the invoice.
  • Technical data sheets, manuals and test reports for regulated items.
  • Certificates such as electrical safety test reports where relevant.
  • Labels and markings on regulated goods in line with Tanzanian requirements.

Worked example: a sunflower oil line

A processor in Singida imports a 20-tonne-a-day sunflower pressing and refining line. Before ordering, the supplier and clearing agent classify each item; most machines are not on the regulated list, but some electrical items and the packaging consumables are. The PVoC inspection is booked for the week of the factory acceptance test in China, the CoC is issued before shipping, and the line clears at Dar es Salaam without inspection delays. The processor also confirms VAT deferment for the capital goods with TRA before the order. The figures and names are illustrative.

Common mistakes

  • Assuming machinery is never regulated, and missing regulated parts and consumables.
  • Booking PVoC after the goods are packed, causing a second inspection or delay.
  • Shipping without the CoC and facing rejection or a fine.
  • Mixing up PVoC and duties, and missing VAT deferment conditions.
  • Vague invoice descriptions that make classification uncertain.

Timing PVoC in the project plan

Build the PVoC step into your project schedule from the start. When you sign the supply contract, list which items are regulated and who will book the inspection. When the factory confirms the date of the factory acceptance test, book the PVoC inspection for the same week and send the documents in advance. After the inspection, allow time for any laboratory tests and for the CoC to be issued before the container is loaded. Only then book the vessel. A delay of a few days at this stage is far cheaper than a fine or rejection at the port.

Keeping records for clearance

Keep the CoC with the commercial invoice, packing list and bill of lading, and give copies to your clearing agent before the vessel arrives. If the CoC lists items or quantities, they must match the invoice and the container. Differences between documents are a common cause of delays at clearance.

Other agencies

Some goods need approvals from other Tanzanian agencies as well as TBS, for example food, chemicals or electrical equipment regulated by sector authorities. Check whether anything in your shipment falls under another agency's rules, especially consumables, chemicals or laboratory reagents shipped with a line.

Where CISH fits

CISH supplies, installs and commissions production lines in Tanzania from audited factories in China. We classify each item, check it against TBS's regulated list and exemptions, sequence the PVoC inspection with the factory acceptance test, and ship only when the documents are in place. The CoC and clearance remain matters between the importer, TBS and TRA; we prepare the line and its documents so that they go smoothly.